Roadworks to close M5 over Christmas

Motorists are advised to plan aheadplaceholder image
Motorists are advised to plan ahead | Google Maps

Part of the motorway will be closed from Christmas Eve to Boxing Day.

A stretch of the M5 near Exeter is to close for two nights over Christmas to allow engineers to complete essential works.

The work, which will take place below the M5 Exminster Viaduct, has been scheduled for the “one period in the year” when no trains will be running on the track below.

National Highways engineers will remove a 50-year-old steel safety deck originally built to prevent debris from potential motorway collisions falling onto the railway line.

The structure was first installed in 1977 and is now “corroded and deteriorated beyond repair”.

The safety deck in place between the southbound and northbound carriageways of the Exminster viaduct  placeholder image
The safety deck in place between the southbound and northbound carriageways of the Exminster viaduct | National Highways

Its removal is scheduled for Christmas Day, Friday, December 25 - the only time of the year that Great Western Railway does not operate its London to Plymouth service.

This means the M5 will be fully closed between junctions 30 and 31 from 8pm on Christmas Eve, Thursday, December 24. The road will re-open at 6am on Boxing Day, Saturday, December 27.

“Our teams have been working closely with National Highways to carefully plan this operation and make sure the work can be carried out safely above the railway,” said a Network Rail spokesperson.

“Scheduling it during the Christmas railway shutdown means the work can be completed when trains aren’t running, helping to minimise disruption for passengers and the wider public.”

An example of the corroded steelwork below the surfaceplaceholder image
An example of the corroded steelwork below the surface | National Highways

Following survey and preparation work, two 150-tonne cranes will be deployed to remove the steelwork. The railway tracks will then be covered with protective sheeting while the structure’s supporting girders are lifted through the gap between the carriageways.

National Highways says there is no need to replace the safety deck as steel infill panels and mesh netting have already been installed.

Terry Robinson, South West engineering lead for National Highways, said: “Many of the roads and bridges we manage were built around 60 years ago and the safety deck has also reached the end of its lifespan and needs removing before it creates a safety risk for trains running below the viaduct.

“Christmas Day is one of the quietest days on our network, and although the closure will still have impacts for the travelling public, we’re expecting these to be minimal.

“We would, however, advise drivers travelling over Christmas to plan ahead, consider alternative routes where possible, and allow extra time for their journeys.”

It is understood diversion routes will be “clearly signed” for anyone travelling during the disruption.

Through traffic on the M5 southbound is advised to exit the motorway at junction 30, follow the A379, and then re-join the A38 at the Matford area.

Northbound traffic should leave the A38, follow the A379, and re-join the M5 at junction 30.

A30/M5 traffic is advised to use the A379/A377/B3123 via Matford/Alphington, while A30/A38 traffic can use junction 31 with no diversion required.