New Heavitree water play area delayed until spring 2027


The new facility will replace the site's old paddling pools, which closed permanently in June after ageing underground pipework and water treatment systems needed replacing.
Plans to reopen a new water play facility at Heavitree Pleasure Grounds in Exeter before the end of summer have been delayed, with the project now not expected to open until next spring.
Exeter City Council said the concrete bases for the new facility were completed this week, but will need a 28-day curing process before further work can continue, meaning the site cannot open before the end of summer as had previously been hoped.
In the meantime, families have been told they can continue to use the Splash Pad in St Thomas, which will remain open for the next few weeks, subject to weather conditions and operational considerations.
Councillor Duncan Wood, lead councillor for leisure services, healthy living and public realm management, said: "We were really hoping to get the new water play facility up and running by the end of September, but unfortunately that is not now going to happen. Instead, we will look towards an opening next spring when the air temperatures start to warm up again."
The new facility will replace the site's old paddling pools, which closed permanently in June after ageing underground pipework, water treatment and filtration systems, pumps, electrical infrastructure and drainage all needed replacing. Once finished, it will include a dedicated shallow water play area for younger children, alongside a larger interactive splash play space with a range of water effects on the site of the old pool.
Work on the surrounding tarmac areas and an enlarged pump house structure is expected to be completed by the end of this week, with mechanical and electrical installation work due to begin the week of September 28. The council said the procurement process for the new play area is also under way, with quotes being sought from potential suppliers and contractors.
The new play area will be built to the north of the existing one, meaning the current play area can stay open throughout construction, giving residents continued access over the winter months. The existing play area will also be refurbished during this time, with some worn-out play equipment removed and improvements made.
Once both projects are complete, the fencing between the two areas will come down, creating a single, larger play space, with new gates linking directly to the water play facility. A combined opening of both the wet and dry play areas is planned for spring 2027.